Normal Street still has its construction fencing between University Avenue and Washington Street. Southbound traffic is closed and there's no street parking on that stretch. SANDAG's Eastern Hillcrest Complete Streets page says that is a "long-term closure until the Promenade is complete," and it still lists the project status as "In Progress: Construction." Much of the park is already in place behind the fence. At a July 21 site tour, the contractor had planted 98 trees and installed the light and shade structures and the concrete seating, Times of San Diego reported.
Back in August, we wrote that the Promenade seemed weeks away. It wasn't. In an October 14 story about Balboa Park, Times of San Diego said in one line that the Normal Street Promenade "will not even fully open until next year." That same story is about a much larger park decision that Hillcrest residents can weigh in on this winter. While Normal Street finishes up, Hillcrest's real voice on park space runs through the 1,200-acre park at the end of Upas Street.
What Normal Street is waiting on
The finished Promenade is still the neighborhood's big new public space. The Hillcrest Business Association describes Pride Plaza, a restored streetcar concession, a shaded playground, seating and bike paths, all running along the block between University and Washington. SANDAG's schedule has the bikeway portion of the project opening to the public in 2027.
The delay also keeps the Sunday market where it is. When the City launched the project, it said the Promenade "will accommodate the weekly Hillcrest Farmers Market." The market's operator calls its current spot temporary while its permanent home is being built. For now, every November Sunday is still at 1601 University Avenue, 9 a.m. to 2 p.m.
Hillcrest's other park is being redrawn
On Wednesday, October 14, the City of San Diego began the first comprehensive update of the Balboa Park Master Plan since 1989. City staff and the outside firm WRT Planning + Design are writing the plan. The nearly $2 million cost is covered by grants from SANDAG, the Prebys Foundation and Caltrans. The finished plan will guide the park for the next 30 years. It covers recreation and facilities, transportation and access, historic preservation, and how the park pays for itself.
The part that matters most to Hillcrest is how the City talked about the park's edges. Andy Field, director of the Parks and Recreation Department, told Times of San Diego that Balboa Park is a regional park and also the local park for some of the city's fastest-growing communities. The same story noted that Bankers Hill and Hillcrest each have only one small park of their own.
Field said the west side of Balboa Park "currently has none of those kinds of facilities," meaning "no athletic fields, no big recreation center."
He also tied the question to growth nearby, citing "extensive residential development" in Uptown. The story said the park edges facing downtown and the Uptown neighborhoods could be redeveloped to suit community needs, and that now is the time for those residents to weigh in.
So the question of what a park on Hillcrest's side should include is open again. The Promenade will be one block long. The west edge of Balboa Park is the larger piece, and its future is now being written.
How long the plan takes
The survey is only the first step. Here is the tentative schedule from the City's September 3 committee presentation:
- Fall 2026: kickoff and framework, the current phase
- Winter 2026: existing conditions
- Spring 2027: ideas
- Fall 2027: first draft of the master plan
- Spring 2028: final draft
- Winter 2028: adoption
The Initial Ideas Survey went live at PlanBalboaPark.org on the October 14 launch day. Times of San Diego reported it would stay open "for the next three months." Questions go to [email protected]. The City also says it will release a Community and Stakeholder Engagement Plan in November 2026 and convene a stakeholder working group. That release will show how the next rounds of input will work.
Some old ideas are coming back. The 1989 plan studied and then dropped a trolley connection to the park, a pedestrian and bike bridge along 8th Avenue, and a parking garage under the Organ Pavilion. Times of San Diego reported those ideas will be looked at again, provided they still fit modern needs. Money hangs over all of it. An August inewsource report found about $1 billion in deferred maintenance in the park. City Planning Director Heidi Vonblum put the timing simply: "When will it happen? It's all dependent on funding."
January 1 changes the parking math on the west edge
A smaller change arrives well before any new design. The City Council approved a settlement that removes paid parking in Balboa Park effective January 1, 2027, according to the City's Balboa Park parking page, last updated August 27, 2026. Paid parking had started January 5, 2026, so the program will have lasted just under a year.
| Through December 31, 2026 | Starting January 1, 2027 | |
|---|---|---|
| General lots, including Marston Point | Free for verified City of San Diego residents after a one-time $5 registration | Paid parking removed |
| Premium lots | Discounted daily rates for verified residents | Paid parking removed |
| Park road meters | $2.50 an hour, up to $10 a day, 8 a.m. to 6 p.m. | Paid parking removed |
| Monthly passes | No longer available for purchase effective November 30 | No longer sold |
The meters on Sixth Avenue between Elm and Upas Streets sit outside the park. They charge $2.50 an hour with a four-hour limit, and the resident discount has never applied to them. Paid parking isn't enforced on Veterans Day or Thanksgiving Day, so two November holidays are already free. Rules like these can change, so check the City's page before you drive to the park.
The west-edge places the survey is about
Nate's Point is the City's off-leash dog area at Balboa Drive and El Prado, just south of the Cabrillo Bridge. It's open 24 hours.
Marston Point is a named park area that hosts special events. Under the current rules it's one of the general lots where verified residents park free.
Sixth Avenue Playground is the City playground on the park's Sixth Avenue side, with its own City general development plan.
Panama 66 and the park's other restaurants bring in sales tax, but Times of San Diego reported they come nowhere near what the maintenance backlog needs.
When Field talks about missing athletic fields and a missing rec center, these are the places he means. The survey is where a Hillcrest resident can say whether the dog park, the playground or something new should come first.
November on the Hillcrest side of the fence
The neighborhood calendar doesn't wait for the Promenade.
- Hillcrest Farmers Market: Sundays, November 8, 15, 22 and 29, 9 a.m. to 2 p.m., at 1601 University Avenue.
- Hillcrest Honors: Monday, November 16, 5 to 9 p.m., listed on the Fabulous Hillcrest calendar.
- Shop Hillcrest for the Holidays: the HBA's promotion runs from Small Business Saturday, November 28, through December 24. Shopping on November 28 earns double entries, and so does shopping on December 10, the night of Taste 'n' Tinis.
On University Avenue, Pali Wine Co. moved its tasting room this summer to 1440 University Avenue, the former Cellar Hand space. FOX 5 described a full kitchen, an outdoor patio, live music on weekends and a weekday happy hour. It's a short walk from the market. A few blocks west, Mr. Charlie's opened July 11 at 3896 Fifth Avenue.
A Sunday at the market can now also include ten minutes at PlanBalboaPark.org.
If you're weighing how Hillcrest's park changes on Normal Street and along Balboa Park's west edge fit into your own plans to stay, sell or buy nearby, Patricia Casanova can walk you through it calmly and at your pace. Let's find your next home. Consulta en español disponible.