Bonita Road Traffic and SR-125 Tolls: What Comes Next

At the Sweetwater Community Planning Group's March 3 meeting, a County project manager reported that Bonita Road now carries about 18,800 vehicles a day at speeds around 40 mph. The road used to carry roughly 10,000. That is close to double. Sunnyside Common Sense covered the meeting. Robert Sanchez of the San Diego County Department of Public Works told the group the growth comes from drivers avoiding the State Route 125 toll.

Two public bodies are now working on that problem, and they are moving at very different speeds. The County plans to change the road itself next spring. The toll that sends drivers onto Bonita Road is on a schedule that, by current estimates, stretches into the next decade. Bonita Road's next several years depend on the gap between those two timelines.

The traffic follows the price of a highway Bonita doesn't control

The South Bay Expressway is the 10-mile stretch of SR-125 from Spring Valley to the U.S.-Mexico border. SANDAG runs it as a toll road. According to inewsource reporting from April 2026, more than 50,000 drivers use it daily and pay from 50 cents to $3.50 depending on distance. FasTrak can cut that by up to 80%. Traffic on SR-125 grew 14.6% between the 2024 and 2025 fiscal years.

A few dollars matters to drivers on this road. In its September 2026 review of the expressway's bonds, Fitch Ratings noted that traffic rose sharply after an earlier toll reduction, which shows "historically high demand elasticity." Drivers on this corridor respond quickly to price. When the toll dropped, traffic moved onto SR-125. The same sensitivity explains why the toll pushes some drivers onto surface streets.

People in Bonita have said this for a while. The County-published minutes from the March 3 planning group meeting record a request to keep pushing for elimination of 125 tolls "to reduce through-traffic in Bonita." At SANDAG's September 11 board meeting, a Bonita resident used public comment to blame most of the 18,800 daily vehicles on toll avoidance through the San Miguel Ranch Road and Proctor Valley Road connector. A Sweetwater Valley Civic Association board member told the board that toll-avoiding drivers were overloading neighborhood roads. Those are community accounts. No County or SANDAG traffic study has published the count or its cause independently.

Supervisor Paloma Aguirre, who represents District 1, wrote in a September recap for Bonita residents that she raised residents' SR-125 concerns at a September 4 SANDAG meeting. She described the upcoming board item as a refinancing plan "to eliminate debt sooner and reduce pass-through traffic on Bonita streets."

Why the toll can't simply be switched off

The SANDAG Board heard that update on September 11 as an informational item, with no vote. The staff report states the constraint plainly:

"The July 1, 2027, bond call date provides an opportunity to pay down and/or restructure the outstanding debt but does not, by itself, allow SANDAG to remove the tolls."

SANDAG has to clear two separate hurdles before it can hand SR-125 back to Caltrans. It has to pay off the bonds, and it has to bring the highway up to Caltrans' "state of good repair" standard under the franchise agreement. The September presentation put the bond balance at $153 million as of July 1, 2026. To pay it down faster, staff outlined three steps:

  • Apply about $23 million in state funds and interest earnings to the debt.
  • Change reserve policies, including the two-year operations and maintenance reserve of about $52.6 million, to free roughly $28 million more when the bonds are called.
  • Consider refinancing the remaining debt in 2027 to pay it off earlier.

The presentation showed a possible full payoff in 2029 or 2030. Paying off the bonds doesn't end the tolls, though. North County Pipeline reported from the same meeting that SANDAG staff expect tolls to continue until 2033 to 2035 because the highway upgrades, environmental review and state handover still have to be completed. That is still earlier than the agency's original estimate of 2037. The repair cost estimates exist in reports still in final review, and the environmental phase is set to refine them.

Price is the other factor. Fitch reported that SANDAG management has no current plans to raise tolls, citing affordability concerns and political pressure to eliminate them. For Bonita Road, that means the gap between the toll and the free alternative will likely stay roughly where it is until the toll goes away.

So the County is working on the road the traffic already uses

The County's near-term project, the Bonita Road Bicycle Safety Improvement Project, assumes the traffic stays. Sanchez told the planning group in March that the project started because of more traffic and more accidents, not because cyclists asked for it. Sunnyside Common Sense reported that the Local Roadway Safety Plan lists it as a top safety priority.

The March presentation as reported by Sunnyside Common Sense described this plan:

  • Limits: Bonita Road from Central Avenue west to the county limits, marked by Bonita Valley Community Church at 4744 Bonita Road.
  • Lanes: one five-foot bike lane on each side of the road.
  • Markings: green paint on the south-side lane at driveways and other "conflict zones."
  • Surface: a slurry seal on the stretch before striping.
  • Signs: two more dynamic speed-warning signs.
  • Footprint: no new right-of-way and no widening. The County minutes add that the existing turn lane stays.

The planning group returned to the project at a special meeting on September 8 and voted 9-1-1 to support it, with four members absent. According to Sunnyside Common Sense's account of the vote, members asked whether a curb barrier would separate the bike lanes from traffic. The answer was no. They asked how drivers would learn about the green lanes, and the answer was signs along Bonita Road. The project had been on hold for lack of money. It needed $600,000 for design and construction, and a $539,000 state grant closed most of that gap.

Paint and signs are tools for managing traffic on a road, and they leave the number of cars as it is. The planning group minutes reflect that debate. Members noted that the County had cited daily car counts but had no count of how many bicycles use the road, and some questioned whether striping alone was worth the cost. Others called it "better than nothing."

Two timelines, side by side

Milestone Timing Status
Bike project goes to the County Board of Supervisors November 18, 2026 Reported by Sunnyside Common Sense. Not yet posted on the County's public meeting calendar.
SANDAG progress update on toll system and processing fees November or early December 2026 Planned in SANDAG staff report
Toll data migration to new back-office partner Expected by December 2026 Planned in SANDAG staff report
SANDAG board discusses bond repayment options Early 2027 Planned in SANDAG staff report
Bike lane construction, about 2.5 months, one lane open Early spring 2027 Reported by Sunnyside Common Sense
SR-125 bond call date July 1, 2027 In SANDAG documents
Potential full bond payoff 2029 to 2030 SANDAG presentation estimate
Tolls expected to end 2033 to 2035 Reported by North County Pipeline
Franchise agreement ends 2042 In SANDAG documents

The bike project's own dates have moved. In March, the County minutes said plans would be finished in late 2026 and construction completed in late 2027. The September report gave a start in early spring 2027 and about two and a half months of work. Expect the Board item, if it goes ahead, to settle the actual schedule.

What the next six months hold for anyone who drives Bonita Road

  1. November 18. If the item stays on the Board of Supervisors agenda, that is the vote that moves the bike lanes toward construction. The County posts Board of Supervisors agendas at least 72 hours before each meeting.
  2. Late November or early December. SANDAG staff return to the board on the new toll system. The update will cover proposed toll processing fees and outreach for a spring or summer 2027 launch. Anyone who drives SR-125 occasionally or pays outside FasTrak will see those fees.
  3. Early spring 2027. Bonita Road narrows to one lane with crews directing traffic for about ten weeks, if the reported schedule holds.
  4. Early 2027 at SANDAG. The board takes up how to structure the 2027 bond repayment. That decision determines whether the 2029 to 2030 payoff estimate holds.

There are direct contacts for local concerns in the meantime. In her September recap, Supervisor Aguirre listed Bonita Community Representative Marianne Delatorre at [email protected]. She also said two dedicated CHP officers now cover Bonita and Lincoln Acres, and residents can request traffic enforcement at [email protected].

If the November vote goes through, crews are scheduled to restripe Bonita Road over about ten weeks starting in early spring 2027. SANDAG's own timeline still has tolls on SR-125 for years after that.

If you're a Bonita homeowner wondering how the bike lane work or the toll timeline could affect a future sale or move, I'm happy to talk it through with you. You can reach me at Patricia Casanova. Let's find your next home — consulta en español disponible.